% Availability does not honor term date in calculation on Resource workloads portlet
book
Article ID: 370645
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
Resource Workload portlet does not show the correct allocations when unit of measure is set to % Availability and resource has a term date.
Steps to Reproduce:
In Classic View
Create a project Start Date = 7/1/2024 Finish Date 7/31/2024
On Team tab, add a resource
Make sure they have 100% allocation
Click on Tasks tab and add a task
Assign the resource to the task
Go to Home>>Resource Management>>Resource Planning
Click on Workload tab
Go to Configure>>List Column Section>>Options
Select % Availability from the Work Effort Unit of Measure drop-down
Search for your resource
You will see that they are assigned 100% during July
Click on the resource name
Enter a Date of Termination = 7/15/2024
Save and Return
Let the Time Slices run or run the Time Slicing job
Expected Result - The allocation will still show as 100% because they are allocated 100% until their term date and they should have no availability after 7/15/2024
Actual Result - The term date is not taken into consideration when using % Availability and updates the allocation to 47.83%