Issue/Introduction

STEPS TO REPRODUCE:

1. Login to Classic Ui.
2. Navigate to Timesheet Options -> set Display Unit to Days.
3. Navigate to Modern UX -> Administration -> Timesheets. 
4. Create a Rule with below options.
    Resource :- Active = Yes
    Timesheet Total :- Timesheet Daily Total != 1
    Message :- Daily total shouldn't be less than or greater 1 day
5. Create second rule with below options.
    Resource :- Active = Yes
    Timesheet Total :- Timesheet Grand Total != 5
    Message :- Weekly total shouldn't be less than or greater than 5 Days
6. Open up a timesheet and add atleast 8 assignments.
7. Populate each assignment with values ranging from 0.05 to 0.20. Essentially we want all the 7 time entries to be filled up in Fractions.
8. Ensure that Daily Total = 1 and the Weekly Total = 5.
9. Submit the Timesheet

Expected Results :- Timesheet is submitted successfully.
Actual Results :- Timesheet is not successfully submitted and throws Timesheet validation error even though the conditions match.

Environment

16.2.1, 16.2.2

Cause

DE80935

Resolution

The resolution for this issue is included in 16.2.3 and 16.2.2.1 (patch 1).