Failed to generate upgrade plan. Could not get interoperability data from VMware Interoperability Matrix to generate Upgrade Planner Report.
search cancel

Failed to generate upgrade plan. Could not get interoperability data from VMware Interoperability Matrix to generate Upgrade Planner Report.

book

Article ID: 369859

calendar_today

Updated On:

Products

VMware Aria Suite

Issue/Introduction

  • When trying to use the Upgrade Planner in Aria Suite Lifecycle Manager you can face issues in generating plans involving vRealize Operations. Resulting in errors similar to:
"Failed to generate upgrade plan. Could not get interoperability data from VMware Interoperability Matrix to generate Upgrade Planner Report. Check if there is internet connectivity from vRSLCM."

 

  • Upgrade Planner is accessible under Environments > Actions > Upgrade Planner


Environment

  • VMware Aria Suite Lifecycle 8.x (formerly VMware vRealize Suite Lifecycle Manager 8.x)

Cause

  • Issue with Aria Operations (formerly vRealize Operations) Product ID as part of the Interoperability Matrix due to change in branding.

Resolution

  • Fix provided as part of VMware Aria Suite Lifecycle version 8.18