Issue:
Finish Date does not consider the user's timezone when Date/Time Format Scale is "Day"
This happens for Tasks and Ideas
Steps to reproduce:
Expected result: The finish date for that Task should convert according to the user's time zone
Actual result: The finish date for the Task does not consider the time zone when Date/Time Format Scale is set to Day
Release: All Supported Releases
Component: PPMPM
DE41866
Sustaining Engineering reviewed and determined this issue will not be fixed
WORKAROUND
Change the display format to Day/Time format.