Steps to Reproduce:
1. Create a calendar 'A' with parent set to the box Standard calendar.
2. Create a calendar 'B' making it a 9 hours per day calendar with parent set to calendar 'A'
3. Create a calendar 'C' making it an 8 hours per day calendar with parent set to calendar 'B'
4. Create a labour resource and set its calendar to 'B', check to ensure its Availability is changed to 9 hours.
5. Run the Timeslice job
6. Change the labor resource calendar to 'C' (8 hours per day), check to ensure that the resource availability is set to 8 hours per day.
7. Run the Timeslice job
8. Check the slice data
Expected: The Availability slices will only contain 8 hours per day
Actual: Availability slice has an entry for 9 hour per day.
Version 16.1.3.
DE78671
Not reproducible in 16.2.0.