How is Baseline Usage Calculated?

book

Article ID: 36108

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction

Question:  

How is baseline usage calculated?

 

Answer: 

Baseline Usage displays the system-generated usage at the time you baseline using the following formula:

Baseline Usage = Total of Actuals + ETC

Notes:

  • Baseline Usage is the term used both by PPM and Open Workbench
  • The equivalent of Baseline Usage in Microsoft Project (MSP) is Baseline Work
  • The equivalent of Remaining Work in MSP is ETC

 

Additional Information:

If you are still not seeing baseline usage calculate correctly, please see the following KBs:

- TEC1503689 - Baseline Usage is not saving back to PPM when baseline is created in MSP using New Driver

- TEC1019129 - Due to a Microsoft Project defect, baselines should only be created in PPM with MSP 2010

See the following Wiki documentation for more details on baseline:

Creating Project Baselines

Baseline Projects in Open Workbench

Also, below is cookbook information regarding baselining with PPM and Microsoft Project:

Baselines in CA Clarity PPM and Microsoft Project