When the start and/or finish dates of a subproject are set outside of the parent start and/or finish dates of the parent project, the parent project start and/or finish dates should be pushed out.
Steps to Reproduce:
Expected Result: That the parent dates will be pushed out as well
Actual Result: They are not and there is an error seen in the logs
Caused by CLRT-79496
This issue is reproduced only in v14.3 which was caused by a fix for CLRT-77804 : Auto-start on update processes launch on hierarchical parents of projects when the start or finish date of the child project is changed
Resolved in CA PPM 14.3 Generic Patch #3
Reference TEC1696455 : PPM 14.3 Generic Patch available to resolve reported issues
Reference KB000097276: Proxy Task Duration Not Calculating Correctly