Regardless of the allocation at the child level, the allocation at the program level is not adding up to the sum of all the children allocations.
If the same resource is placed on multiple subs and those subs are included in a master, when viewing the Resource's % allocation in a time-phased cell the value is wrong if the total sub availability is less than 100%
Steps to Reproduce:
Expected Result: Allocation of the resource should be 50% for February and November
Actual Result: Allocation of the resource is 100% for February and November
Applies to all supported PAS environments for specified releases.
Caused by CLRT-79058
Fix: Curves for the subprojects are merged before creating the curve for the master project or program.
Resolved in CA PPM 14.3 Generic Patch #2
Use 'Unused Availability' formatted as a percentage in the view.
Reference TEC1696455 : PPM 14.3 Generic Patch available to resolve reported issues