Baseline Usage is not saving when baseline is created in MSP using New Driver

book

Article ID: 35722

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

If a baseline is created in Microsoft Project (MSP) using the new MSP Interface driver, team Baseline Usage/Baseline Work is wiped out when saving back to Clarity.

Steps to Reproduce: 

   1.  Create a project in Clarity 

   2.  Add a resource to the Team tab (Issue happens regardless of whether resource is hard booked or not) 

   3.  Export the project to MSP

   4.  Create task and assign resource with ETC

   5.  Create a baseline (Project -> Set Baseline) 

   6.  Add Baseline Work to the Resource View

   7.  Save back to Clarity

   8.  Navigate to the Team tab and add Baseline Usage to the Team view

Expected Result: Baseline Usage matches that which was in MSP for Baseline Work prior to saving back to Clarity

Actual Result: Baseline Usage is deleted (reduced to zero). 

Note: If you export the project to MSP, Baseline Work is also deleted out at the Resource level, though Baseline Work is okay at the task level there. 

Cause

This is caused by CLRT-79581

Environment

New Driver for Microsoft Project Interface 

Release: 14.2 patch 6 and 14.3

Resolution

This issue is no longer reproducible in Clarity 14.4

Workaround: 

Create the Baseline in PPM.

  1. Navigate to the project in PPM.
  2. Select the Properties drop down then Baseline.
  3. Click 'New' then enter required information and click 'Save and Return'. 