[VMC] Request to upgrade SDDC or reschedule/postpone a pending upgrade
book
Article ID: 320329
calendar_today
Updated On:
Products
VMware Cloud on AWS
Issue/Introduction
The SDDC needs to be upgraded due to a compatibility issue or an update to correct an ongoing issue.
A pending SDDC upgrade needs to be rescheduled or postponed due to production impact or maintenance window.
Environment
VMware Cloud on AWS
Resolution
To request an SDDC to be upgraded, or to request a pending upgrade be rescheduled or postponed, work with the organization's account team to schedule the upgrade.
If the organization does not have a representative, open a ticket with the VMC on AWS Global Support team. Include the following information:
Organization ID
SDDC ID
Current version
Business justification (these can include compatibility reasons, implemented fixes, keeping linked SDDCs at the same versions, etc.)
Date and time of the requested update (The VMC team recommends requesting at least two weeks for the upgrade date and time)
Note: VMC on AWS SDDC upgrade schedules can be requested by submitting an "Upgrade Schedule Request" through the VMware Cloud Console.