Issue/Introduction
This article provides recommended steps to perform before a planned migration of vRealize Operations from Region A to Region B when vRealize Operations Manager remote collectors remain accessible.
Environment
VMware Validated Design for Software-Defined Data Center (SDDC) 4.2.x
VMware Validated Design for Software-Defined Data Center (SDDC) 4.3.x
VMware Validated Design for Software-Defined Data Center (SDDC)
Resolution
Note: The FQDNs and node names below are examples. Replace the FQDNs and IPs as needed.
Perform the following steps before Initiating a Planned Migration of the Operations Management Applications.
- Log in to vRealize Operations Manager Primary Node's admin UI at https://vrops01svr01a.rainpole.local/admin as the local admin user.
- Under Cluster Status, click Take Offline.
- In the take cluster offline dialog box, enter reason and click OK, then wait for the cluster to go into offline mode.
- Initiate Planned Migration of the Operations Management Applications as define in:
- After failover is completed successfully, log in to UI with the above credentials.
- Under cluster status, Select bring online option. Wait for the cluster to go into online mode.