Windows Tile smoke-tests fails for isolation segment segments in Tanzu Application Service for VMS v2.11
search cancel

Windows Tile smoke-tests fails for isolation segment segments in Tanzu Application Service for VMS v2.11

book

Article ID: 298295

calendar_today

Updated On:

Products

VMware Tanzu Application Service for VMs

Issue/Introduction

A bug was introduced in the latest release of smoke-tests bundled in Tanzu Application Service for VMs (TAS for VMs) v2.11 where the BOSH release is missing isolation segment fields for the windows job.
Summarizing 2 Failures:  
            
          [Fail] Isolation Segment Workflow Default isolation segment - Compute isolation disabled.  [It] can be pushed and connected to the `default` isolation segment   
          C:/var/vcap/data/compile/smoke-tests-windows/smoke-tests/isolation_segment_test.go:208  
            
          [Fail] Application Workflow Linux Applications [It] can be pushed, scaled and deleted   
          C:/var/vcap/data/compile/smoke-tests-windows/smoke-tests/base_test.go:38  
            
          Ran 3 of 7 Specs in 262.030 seconds  
          FAIL! -- 1 Passed | 2 Failed | 0 Pending | 4 Skipped  
          --- FAIL: Test (262.03s)  
          FAIL  
          Smoke Tests Complete; exit status: 1  
            
Stderr     -
Task 47836 | 17:46:42 | Preparing deployment: Preparing deployment
Task 47836 | 17:46:42 | Deprecation: Top level 'properties' in addons are deprecated. Please define 'properties' at the job level.
Task 47836 | 17:46:43 | Preparing deployment: Preparing deployment (00:00:01)
Task 47836 | 17:46:43 | Running errand: windows_diego_cell/45d6d266-d5f0-4946-8b63-157316386a24 (1) (00:09:02)
L Error: Response exceeded maximum allowed length
Task 47836 | 17:55:45 | Error: Response exceeded maximum allowed length

Task 47836 Started Thu Oct 7 17:46:42 UTC 2021
Task 47836 Finished Thu Oct 7 17:55:45 UTC 2021
Task 47836 Duration 00:09:03
Task 47836 error


Running errand 'smoke_tests_windows':
Expected task '47836' to succeed but state is 'error'
Exit code 1
===== 2021-10-07 17:47:41 UTC Finished "/usr/local/bin/bosh --no-color --non-interactive --tty --environment=10.1.81.2 --deployment=pas-windows-e99e10c17fcbe4342b29 run-errand smoke_tests_windows --instance windows_diego_cell/first"; Duration: 545s; Exit Status: 1


Environment

Product Version: 2.11

Resolution

R&D is in the process of working on a fix for this issue.

Workaround

In the meantime, we recommend skipping the smoke-tests on the new tile (Ops Manager > Tile > Errand config) until the fix is released.

Note: *This KB article will be updated once the fix is released*