Total Allocation distribution wrong using Duration

book

Article ID: 282647

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

  1. The Allocation is not distributed evenly among the selected periods when the view options are changed from Periods to Duration.

    Steps to Reproduce:

    • Login to MUX
    • Configure the Unit of Measure as Hours from settings in the MUX
    • Navigate to any project in MUX and access the Staff tab
    • Configure the View Options as shown below Periods: Weeks, Type: Periods, Start Period: Apr 08 2024, End Period: Apr 22 2024, Totals: Sum of Periods

     

    • Update the Totals Allocation as 90
    • Observe that 90 is distributed evenly among the 3 periods with 30 hours each
    • Now configure the View options again as shown below. Change the Type as Duration, Start period as Apr 01 2024, Number of periods as 5

     

    • The number of per-periods metrics available in the view are 5 periods now starting from Apr 01 2024 to Apr 29 2024
    • Update the Total Allocation to 60


    Expected Results:
    The allocation hours 60 should be distributed from the complete duration i.e. for 5 periods in the view from Apr 01 2024 to Apr 29 2024

    Actual Results:
    The allocation hours 60 gets distributed among the periods selected in the previous view i.e. for 3 periods from Apr 08 2024, End Period: Apr 22 2024

    Configure the column Per-Period Metrics - Allocation from columns fly out

Environment

Clarity 16.2.1, 16.2.2, 16.2.3

Cause

 DE80562

Resolution

DE80562 is fixed in 16.3.0 (Targeted to release November 2024) and also backported to 16.2.3 patch 1