Non-Admin users report not seeing the Options for the Microsoft Project integration when looking at the under Tasks on a Project. If the user is granted Admin access, then the options are viewable.
For example, without Admin rights, they see:
After being granted Admin rights, the user then can see the options:
Clarity 16.2, 16.2.1
The "Scheduler Format" attribute was made a "Secured Attribute."
Under Administration > Attributes, change the setting/checkbox for "Secure" or add the appropriate group to View / Edit access