Populate from Task Assignments is missing
search cancel

Populate from Task Assignments is missing

book

Article ID: 281452

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

You have a project with a Cost Plan.  You click on the Actions for Cost Plan but 'Populate from Task Assignments' is not an option to choose.

Cause

There are no assignments in the project

Resolution

To be able to populate by assignments, there needs to be resources assigned to at least one task.