Advanced Reporting Simple Type Schedules are changed when Daylight Savings is observed
book
Article ID: 281185
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
Steps To Reproduce:-
Login to Clarity. Navigate to Advanced Reporting.
Right Click on a Report and Click on Schedule and then "Create Schedule".
On the Schedule Tab, select "Recurrence Type" as "Simple" and Select the Time zone as "Eastern Standard Time".
Set the start date as a specific date and set a specific time as "9:00 AM".
Set the parameters and schedule.
Validate the execution time when DST starts or Ends.
Expected Results :- The Report Execution time doesn't change. Actual Results :- Report executes late by an hour or early by an hour.
Resolution
As a workaround you need to use the Calendar type recurrence type and set the report execution time. This will ensure that DST doesn't impact the execution time of the report.