How to create an extended calendar for the day next to first workday of month?
search cancel

How to create an extended calendar for the day next to first workday of month?

book

Article ID: 280764

calendar_today

Updated On:

Products

Autosys Workload Automation

Issue/Introduction

How to create an extended calendar where the requirement is:

1) Mon-Fri  are WorkDays

2) Sat/Sun  are Non Workdays

3) Goal is to run a job on the next day to the first Workday of month.   So, if first Workday of month is Friday, job should run on Saturday. 

Resolution

Create an Extended Calendar with below definition:

condition: WORKD#1

Adjustment = 1     

Non-Workday Action:   Schedule Anyway ignoring workdays

Additional Information

For more information on the allowed condition keywords, refer to: https://techdocs.broadcom.com/us/en/ca-enterprise-software/intelligent-automation/autosys-workload-automation/12-1/scheduling/ae-scheduling/manage-your-calendars/date-condition-keywords.html