How to create an extended calendar where the requirement is:
1) Mon-Fri are WorkDays
2) Sat/Sun are Non Workdays
3) Goal is to run a job on the next day to the first Workday of month. So, if first Workday of month is Friday, job should run on Saturday.
Create an Extended Calendar with below definition:
condition: WORKD#1
Adjustment = 1
Non-Workday Action: Schedule Anyway ignoring workdays
For more information on the allowed condition keywords, refer to: https://techdocs.broadcom.com/us/en/ca-enterprise-software/intelligent-automation/autosys-workload-automation/12-1/scheduling/ae-scheduling/manage-your-calendars/date-condition-keywords.html