When looking in audit you can see Update Investment Allocations job set Project Schedule Finish to a value taken from curves and then set it back immediately after that and within the same minute. This happens on one project 2 times in the space of few months.
STEPS TO REPRODUCE:
Expected Results: The Update Investment Allocations job not to be updating the schedule start and finish dates back and forth
Actual Results: In audit, you see admin user and Investment Allocations updates the project finish to one value, then sets it back to initial value immediately after
Note: This behavior also applies to Start/Finish dates on Staffing/Team object and is not solely limited to Project dates.
All Supported Clarity Releases
This is DE79988, reviewed by Engineering and set to Won't Fix
Product Management will keep this concept in mind as we progress with enhancements in this area.