Auto Schedule in MUX Critical Path Not Show until Publish
search cancel

Auto Schedule in MUX Critical Path Not Show until Publish

book

Article ID: 280646

calendar_today

Updated On:

Products

Clarity PPM On Premise

Issue/Introduction

Critical Path does not calculate in MUX until you publish.  In Classic Gantt you can see the critical path before you publish the tentative schedule. 

 

STR:

1)  Create a project that has tasks and dependencies.

    - If you have the Major Project Template you can use that.

 

2)  In Classic open the gantt and add the Critical attribute

 

3)  Run Auto Schedule with Options

    - Leave options as they are

    - Note that the critical tasks are marked based on the Auto Schedule before you publish the schedule

 

4)  Perform the same steps in MUX

    - you can delete the tasks from the project and copy tasks from the template again as well

 

5. Under Actions choose Autoschedule - do not choose any additional options

 

Expected Results:  Before you actually publish you should see the critical path which is what you see in Classic

Actual Results:  The critical path only shows once the schedule is published

 

Workaround:  none

Cause

Reported as DE79975. 

Resolution

 DE79975  resolved in 16.2.2