Critical Path does not calculate in MUX until you publish. In Classic Gantt you can see the critical path before you publish the tentative schedule.
STR:
1) Create a project that has tasks and dependencies.
- If you have the Major Project Template you can use that.
2) In Classic open the gantt and add the Critical attribute
3) Run Auto Schedule with Options
- Leave options as they are
- Note that the critical tasks are marked based on the Auto Schedule before you publish the schedule
4) Perform the same steps in MUX
- you can delete the tasks from the project and copy tasks from the template again as well
5. Under Actions choose Autoschedule - do not choose any additional options
Expected Results: Before you actually publish you should see the critical path which is what you see in Classic
Actual Results: The critical path only shows once the schedule is published
Workaround: none
Reported as DE79975.
DE79975 resolved in 16.2.2