Unable to schedule report distribution in DLP
search cancel

Unable to schedule report distribution in DLP

book

Article ID: 280164

calendar_today

Updated On:

Products

Data Loss Prevention Enterprise Suite

Issue/Introduction

After migrating the system to 16.0.1, unable to click save copy button as it is grayed out on the Schedule Distribution page.

Environment

Release: 16.0.1

Cause

The required fields are empty



Resolution

The functionality is working as per design.

The feature is designed in such a way that if you do not fill the mandatory fields i.e. the labels marked with asterisk (*), the DLP application will not enable the save copy button thus blocking the feature.

Once if all the mandatory fields are filled with data the feature is enabled i.e. marked in yellow as per below screenshot