Allocate from Estimates is increasing the ETCs on the Effort Task
book
Article ID: 279712
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
Allocate from Estimates is increasing ETC when using an effort task. This investment also has regular WBS Tasks with ETC as well.
Steps to Reproduce:
Create a Project with one resource on the team, an effort task and a regular task
Make sure the default allocation for the resource is zero
On the Task tab add 8 ETC to the regular task and make sure the effort task has 0 ETC
On the team tab, click Actions>>Allocate from estimates
You will see the resource has 8 ETC now
Click Actions>>Allocate from Estimates
Expected Results: There will be no change. The ETC for the resource matches the ETC for the tasks
Actual Results: The ETC will increase by 8 each time you Allocate from Estimates even with no changes made
Workaround: Do not use effort tasks
Environment
16.1.3
Cause
DE78960
Resolution
Fixed in 16.2.2
The Effort Task ETCs are now excluded. Only regular Task ETCs are added into the Allocation. The Effort Task, is special and will reflect the Allocation amount.