Copy Cost Plan does not populate the Actual Cost values
STEPS TO REPRODUCE
1. Login to 16.2.0 Clarity machine
2. Navigate to MUX - Projects
3. Click on a financially enabled project and navigate to Financials Tab
4. Create a new Cost Plan and make sure there are Actual Cost showing up in the Actual Cost Totals column and the periods
5. Using the Copy functionality, create a new CP from the CP created in Step 4
Expected: The CP is created and the Actual Cost is reflected in the new CP
Actual: The CP is created but only the planned cost is copied over. The Actual cost remains 0
Workaround:
1. Update the Planned Cost in the grid that shows a Refresh button on the top and once refresh is done, Actual Cost is populated.
2. Change the Cost duration in the CP list page and this will force a refresh and Actual cost will be updated.
DE79365 - Fixed in 16.2.1