The allocation values for Team investments are not correct after an Allocate From Estimates action if a Staff member has got calendar exceptions
STEPS TO REPRODUCE:
Admin > Project Management > Settings > Set Round Allocations to Nearest % to 0
Go to Classic PPM > Admin > Resource Management > Resources
Edit any 2 resources and go to their calendar tab
Set the 1st of January as non-working day
Go to MUX > Teams > Create an Investment team
Start and Finish Dates can be set to 01/01/2024 – 31/03/2024
On the Staff tab, add only one of the above resources
Ensure the Default Allocation % is 100% and set effort to Days
Create a project that spans from the 01/01/2024 to the 31/03/2024
Add to the Staff tab, the team investment and the second resource whose calendar we modified and is not part of the team
Default allocation % for both Staff members set it to 0
Go to Tasks and create one with the same project dates. Assign both Staff members. Add 10 days of ETC per period
Go to the Staff tab and add Allocation per period metrics
View options > Set the decimals display to 0.00
Select both team members and Allocate from Estimates
Check the allocation values
Expected Results: The ETC hours are copied to the allocation of the team members Actual Results: The team type resource allocation value for the month where there is a calendar exception is not correct
Environment
16.2.0
Cause
This is caused by DE79605
Resolution
The affected code area needs to be reworked and it can not be addressed as a defect fix.
Engineering has decided to close the defect and a user story has been filled to address the work needed to change the current design