Copying an Annual Cost Plan spreads Actual Costs throughout the year
search cancel

Copying an Annual Cost Plan spreads Actual Costs throughout the year

book

Article ID: 278823

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

When you copy a Cost Plan with Annual periods and Actual Costs, the copied plan spreads all Actual Costs uniformly throughout the year.

Steps to Reproduce:

  1. In the Modern UX, copy a Cost Plan that has Annual Periods and Actual Costs. For example, it has Actual Costs due to a transaction in February 2024, with a value of $1,200.
  2. Open the new copied cost plan.

Expected Results: When configuring Monthly periods to find the Actual Costs value, the values shown are the same as in the original Cost Plan. For example, February 2024 has a value of $1,200.

Actual Results: When configuring Monthly periods to find the Actual Costs value, the total Annual value has been spread uniformly throughout all the year. For example, all months in 2024 have a value of $100 (even for periods that are in the future, if applicable).

Environment

Clarity 16.1.1.

Resolution

This issue is not reproducible in Clarity 16.2.0 and higher.