MUX Audit Trail Schedule Finish Midnight Date Issue
search cancel

MUX Audit Trail Schedule Finish Midnight Date Issue

book

Article ID: 278650

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

In MUX Audit when there is a midnight date, such as on schedule finish for Ideas the audit in MUX shows +1 day somewhat reflecting what is in the db.  Most places in Clarity take into consideration the midnight date and adjust the views in the UI accordingly.  However in the Audit Trail in MUX the date reflects as the next day.

 

STR:

1) Add the Schedule Finish to the Idea object Audit Trail

 

2) Add Audit Trail to your Idea Blueprint

 

3) Create and Idea

   - Note the Finish Date

   

4) Check the Schedule Finish in the Audit Trail

 

Expected Results:  Finish Date is what you entered and what shows as the Finish Date in the UI

 

Actual Results:  Finish Date is the next day.

 

If you change the Schedule Finish the same thing happens on Update operation

 

Workaround:  View in Classic Audit Trail

Environment

16.1.3 and 16.2

Resolution

Reported as DE7919.  Resolution targeted for 16.2.2.