Baseline disappears after two MSP roundtrips
book
Article ID: 276733
calendar_today
Updated On:
Products
Clarity PPM On Premise
Clarity PPM SaaS
Issue/Introduction
A baseline that contains no tasks disappears from Clarity after loading and saving a project from Microsoft Project twice.
Steps to Reproduce:
- Create a new blank project.
- Create a new baseline for the project.
- In the Baselines page, as well as in the project Schedule & Performance page, check the baseline details.
Expected and Actual Results: Baseline Dates show values.
- Open the project in Microsoft Project.
- Save the project back to Clarity (no difference if there are any changes to the project or not).
- In the Baselines page, as well as in the project Schedule & Performance page, check the baseline details.
Expected Results: Baseline Dates show values.
Actual Results: Baseline Dates are empty.
- Open the project in Microsoft Project.
- Save the project back to Clarity (no difference if there are any changes to the project or not).
- Check the Baselines Page.
Expected Results: No changes to the baseline.
Actual Results: The baseline has been deleted.
Resolution
This issue has been fixed in Clarity 16.2.2.
After upgrading Clarity, upgrade the Microsoft Project Interface as well.