Unable to create Task Dependencies for Project Template from New UI
search cancel

Unable to create Task Dependencies for Project Template from New UI

book

Article ID: 275133

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Creating task dependencies on Project template in NEW UI gives an error CMN-0009: Attribute 'odf_grand_parent_id' has invalid Lookup Value 'xxxxxxx'. The same action works in Classic UI.

Steps to Reproduce

  • Navigate to New UI-> Project Tiles
  • Create a new template or use any existing template
  • Navigate to Tasks tab timeline view
  • Create three tasks
  • Create dependency form Task1 to Task2

Expected Results: The dependency should be created on the tasks

Actual Results: The dependency is not created and it gives an error CMN-0009: Attribute 'odf_grand_parent_id' has invalid Lookup Value 'xxxxxxx'. The xxxxxxx is the projected

Workaround: Use Classic UI to create task dependencies on project templates

Cause

DE78078

Resolution

This issue has been fixed in Clarity 16.2.1.