STEPS TO REPRODUCE:
Create tentative Gantt schedules which locks the projectRemove the lock with a GEL script or security.locks prior to 16.1.1
Expected Results: Orphans not to be in PRJ_TENTATIVE_SCHEDULES
Actual Results: Orphans in PRJ_TENTATIVE_SCHEDULES that can cause duplicates in Project Grid due to a left join in the query
Logged as DE77301 and is resolved in 16.2.0