On 16.1.3 any jobs/report schedules go into Not Scheduled post BG restart
book
Article ID: 273853
calendar_today
Updated On:
Products
Clarity PPM On Premise
Clarity PPM SaaS
Issue/Introduction
Steps to Reproduce:
- Do not pause any Scheduled, Processing or Waiting status jobs and reports.
- Stop and Start all services.
- Observe Job and Reports schedules statuses go into Not Scheduled status.
Expected Results: It should not change schedule status of the jobs/report
Actual Results: It updates status to Not Scheduled.
Workaround: Restart all non-scheduled jobs post upgrade
Resolution
This issue is fixed in Clarity 16.1.3 patch #1 and 16.2.0.
As a good practice prior to any maintenance or upgrade, pause your jobs.