We would like to deploy the Timesheet approval in the MUX. The requirements are for a 2-level approval, with the Project managers and Resource Manager to approve in the MUX.
Release : 16.1.3
As OOTB the feature is that either a Project Manager or Resource Manager whoever approve it first then the status will go Approved.
Regarding the requirements are for a 2-level approval - Please raised an idea/innovation calls/enhancement