Tasks From Parent Moved When Child Was Added
search cancel

Tasks From Parent Moved When Child Was Added

book

Article ID: 273023

calendar_today

Updated On:

Products

Rally SaaS

Issue/Introduction

All the tasks of a story moved to a different story when it had a child added

Environment

Release : 2018

Cause

When you create child stories underneath an existing story, you are telling the CA Agile Central tool that the scope of work is too large to fit into a single iteration. Because the work is now being done in the child stories the tasks that represent that work are moved to the child stories.

Resolution

If a User Story has tasks assigned to it, those tasks will automatically be moved to the new child story.