If you have a custom investment/project with staff and task module, you can use the task field “Assigned Resources” to add or view assigned resources to a task. If the value of an existing resource is getting inactive, you cannot copy the values from one field to another field in grid view.
You will get the error: CMN-0009: Attribute 'Assigned Resource' has Invalid Lookup Value'
The copy from action in timeline view allows you to copy the assigned resources.
Steps to Reproduce:
Expected Results: Entries are copied atleast the active resources
Actual Results: Error message occurs:
CMN-0009: Attribute 'Assigned Resource' has Invalid Lookup Value'
Release : 16.1.3
DE77459, in review by Engineering