What are the best practices in configuring the Administration > Data Administration > Time Slices page?
All Clarity versions
Based on the amount of data and the reporting needs of each implementation, the time slices need to be configured properly.
Make sure the environment performs optimally by ensuring the time slice definitions are set as follows:
The idea is to limit the number of DAILY slice records.This will create fewer records for reporting historical data within the recommended configurations.
Note: If you need past historical data to be sliced for dates further back than what is recommended above, it is recommended to consult our CA Services team for advice on alternative configurations OR use monthly time slices.
Make sure there are not any daily slice definitions that cover a range of over 2 years, especially the team slices.
DAILYRESOURCEESTCURVE
From Date = Start of the current month (There is no need to slice estimates far in the past)
Number of periods = 400 days
DAILYRESOURCEACTCURVE
From Date = Start of the current month, going back 1 year
Number of periods = 740 days
DAILYRESOURCEBASECURVE
From Date = Start of the current month, going back 1 year
Number of periods = 740 days
DAILYRESOURCEAVAILCURVE
From Date = Start of the current month, going back 1 year
Number of periods = 740 days
Note: When a Resource has a Hire Date and/or Termination Date, the Availability slices are bound for the resource within this date range.
DAILYRESOURCEALLOCCURVE
From Date = Start of the current month, going back 1 year
Number of periods = 740 days
If you are not maintaining allocation at the Project level company wide, you may have no need to maintain slice data for allocation. This is by far the largest portion of slice data, and if it is not entirely valid it can be dramatically reduced. We recommend that if you do not set project level allocation you should set the Number of Periods to four (4) for Allocation slice request. This will minimize the amount of data that is being stored for Allocation slices and also populate in the Datamart tables.
If you are truly using this allocation data it should also be in the same range as Baseline and Availability Time Slice definitions. We recommend that you enforce setting project allocations company wide and be sure to properly zero out any remaining/unused allocations. If allocations are set properly on active projects only valid data will be stored in timeslice therefore dramatically reducing the amount of records needed to maintain allocations.
We also recommend that you zero out "Remaining Allocation", as seen on the Project Roster/Team page, for inactive/closed projects. To zero out the resources "Remaining Allocation", we recommend that you set the allocation finish date to the last date the resource worked on the project. "Remaining Allocation" takes into account the last date the actuals were tracked by the resource. This date should be set as the allocation finish date if the resource is no longer working on the project. Zeroing out any unnecessary Remaining Allocation will reduce the amount of data stored in timeslice, and make your data more realistic. The easiest way, although less accurate way to release unused resource allocation, is to ensure ETC is zero and then click "Allocate From Estimates" button on the Roster/Team page. This method of using the "Allocate from Estimates" button for resource with zero ETC is provided as a quick and easy method to zero out allocation. If this doesn't meet your specific needs, use the recommended method, stated above, because it more closely reflects reality.
Once the changes are made and saved complete this step
If reviewing the Time-Scaled Values and there are grid cells that do not allow cell-editing or do not have expected values populate beyond a particular date per the TSV limits,
review the Time Slice IDs: 1, 2, 3, 10, 11 above.
These are the slice IDs that drive the ability to have user edit the time-scaled values.
If the best practices/time slicing configuration is made, proceed to run the jobs to ensure cell-editing is allowed
Also check Configuring the Data Warehouse Time Slices