Changing Blueprint Effects All The Projects Using That Blueprint
search cancel

Changing Blueprint Effects All The Projects Using That Blueprint

book

Article ID: 272399

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

You have made a change to the Blueprint and notice that all the previous projects now reflect the change.

Is there a way to make changes to Blueprint without making any changes to the existing Projects?

Environment

Release : 16.1.2

Resolution

Modifying the blueprint will affect ALL templates and history which is part of this blueprint.
Modifying template will affect go-forward changes for subsequent usage of that template.

Consider using new Blueprints when changes are required. Also consider Project Templates to see if they solve your requirement.

Additional Information

Configuring Blueprints for Projects