Dates are not properly displayed in Modern UX using Portuguese locale
search cancel

Dates are not properly displayed in Modern UX using Portuguese locale

book

Article ID: 271996

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Dates are not properly displayed in Modern UX using Portuguese locale  

STEPS TO REPRODUCE: 
1. Login to MUX and set the user 'Locale' to Portuguese 
2. Log out and log in for chages to take effect
3. Open a specific project and go to the properties tab
4. Check the Start and Finish Date fields 

Expected Results: Start/Finish Dates are displayed properly. 

     INÍCIO: 1 de ago. de 2023
     TÉRMINO: 4 de set. de 2023

Actual Results: Start/Finish Dates are not displayed properly. 

     INÍCIO: 1 '1E' ago '1E' 2023
     TÉRMINO: 4 '4E' set'4E' 2023

Environment

Clarity 16.1.3

Cause

This is caused by DE77334

Resolution

This is fixed in 16.2.0 

The defect fix can not backported to 16.1.3

This issue is reproducible due to migration of date picker to stenciljs and dayjs. The fix does not work for angularjs-based date picket instance. Hence can not be fixed in 16.1.3.1

 

 

Additional Information

A similar defect was seen in the past

Clarity: Start/Finish Date is not displayed properly in New UX when language is set to Portuguese