Timeline view not auto-refreshing when adding assignments
search cancel

Timeline view not auto-refreshing when adding assignments

book

Article ID: 270286

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

When adding assignments into child tasks in the timeline view, auto-refresh is not working (e.g: ETC, Assigned Resources... are not refreshed).

Steps to Reproduce:

  1. Create a new project with a team member.
  2. Navigate to the project tasks module and open the Timeline View.
  3. Add a new task.
  4. Right-click on the task and Insert Child. In the Details flyout, add the team member as an assignment.

Expected Results: After the assignment is added, both child and parent task values (such as ETC, Assigned Resources...) are refreshed.

Actual Results: After the assignment is added, both child and parent task values (such as ETC, Assigned Resources...) are refreshed. If a sibling task (from the child task) is added, the summary task values are refreshed, but not the child task values.

Environment

Release : 16.1.0

Cause

DE71048

Resolution

This issue is under review.