SUMMARY:
The Target Manager from an Idea is not copied over to the Project Manager after converting the Idea into a Project.
Steps to Reproduce:
1. Create an Idea (Classic or Modern UX) or use an existing one.
2. Make sure the Idea is filled in with a Manager and a Target Maganer (both being set different)
3. Submit for approval and approve the Idea. Once this is done, convert it to a Project.
Expected Results: The Manager in the Project is set according to the Target Manager in the Idea.
Actual Results: The Manager in the Project is set according to the Manager in the Idea.
Release : 16.1.2
This has been reviewed as DE70962.
Issue has been addressed. Resolution is included in 16.1.3
Workaround: none