You have a resource whose termination date is on 30/Jun/2023. You see that the Allocation in the 'Team' tab ('Staff' tab in Modern UX), gets set to 0, for July 2023 and thereafter. However, you notice that ETC against Assignments in the 'Tasks' tab, remains for July 2023 and thereafter. Is this expected?
Version: 16.1.2
This is an expected behaviour. ETC has to be manually shifted to a different resource by the Project Manager.