The Effort spent is not populating on the Project Tile or the Status Report, what would be the reason for this?
Release : Any
The Effort metrics on the Status Report are the actual Effort labor actuals (i.e. timesheets posted by resources).
This should display the Effort correctly with the Actuals on this project. Example: