Actuals on Ideas
search cancel

Actuals on Ideas

book

Article ID: 268543

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

Do actuals on Ideas carry over to a project when the idea is converted?

Environment

Release : 16.1.1, all

Resolution

 Actual hours on idea do not transfer to the project when idea is converted

One reason is the idea can be converted several times.

You can link the idea to the project in order to get total hours/costs for associated idea and projects.

Adding all to a hierarchy would be a good way to see all hours/costs roll up.