Do actuals on Ideas carry over to a project when the idea is converted?
Release : 16.1.1, all
Actual hours on idea do not transfer to the project when idea is converted
One reason is the idea can be converted several times.
You can link the idea to the project in order to get total hours/costs for associated idea and projects.
Adding all to a hierarchy would be a good way to see all hours/costs roll up.