You can not have two independent team allocation entries for the same resource at the same project. 

The request status is global for the resource at a given project.

Request Status:

Specifies the requisition status when a requisition is linked to the team record. Project managers use the request status to monitor the state of their requisitions and to book manually a resource without using a formal requisition. The field is read-only when the request status is New, Open, or Proposed, or when no requisitions exist. Values:

New: The staffing requirement is new. The project manager has not requested staffing needs.
Open: The resource requisition is active and is waiting to be filled.
Proposed: The resource requisition has been proposed.
Booked: The project manager has accepted the proposed resource.
Closed: No requisitions are associated with the team member.
Rejected: The request to staff this resource or role to the team for this investment was not approved.