Issue/Introduction

For Compliance Event Manager (CEM) 6.0, what are the minimum number of started tasks to be started and the order of startup: CEMEMUF, CEMERTR, CEMMON, CEMLOGGR , CEMALERTS? These were the started tasks that were started under CM 2.0.

Environment

Release : 6.0

Resolution

The started tasks are mostly the same from CM (Compliance Manager) 2.0, just with the updated names. The order should remain the same as well so it should be:

CEMEMUF
CEMESRVR
CEMERTR
CEMMON
CEMLOGGR
CEMALERT
CEMELDAP
CEMETOM