Issue/Introduction

You have created a process in to trigger when a new ToDo is added/removed in a Task. The start condition on update of Total To Do attribute in Task object is not triggering when you add a new ToDo in Task even after the Total To Do field is updated.

Process conditions allow the user to select Virtual Attributes

Steps to Reproduce: 
1- Studio - Processes - New Process
2- Base it on the Task object, configure it to Auto Start
3- In Condition Builder, you csn select Virtual Attributes

Expected Results: Virtual and aggregated calculated attributes are NOT available for selection in the condition builder

Actual Results:  Virtual and aggregated calculated attributes ARE available for selection in the condition builder

Workaround: 
Do not select a Virtual attribute in the condition builder

Environment

Release : 16.1.2

Resolution

https://techdocs.broadcom.com/us/en/ca-enterprise-software/business-management/clarity-project-and-portfolio-management-ppm-on-premise/16-1-2/administration/configure-processes.html

Beginning with Release 15.4, a Task or Project object process condition cannot include a virtual attribute or aggregated calculated attribute. These attributes are no longer available for users to select in the expression builder when defining a process condition.

----------------

    DE70329 opened to fix the display.