Staff wrongly allocated when using FTE as effort and Grand Totals on the view options
STEPS TO REPRODUCE
1. Create a project with 01/05/23 - 31/07/23 start and finish dates
2. Add a Staff member with allocations 01/06/23 till 30/06/23
3. Set effort in days
4. View Options > Add Allocation, Hard Allocation to the Per-Period Metrics
Set the Start period: Project Start
Set the Finish period: Project Finish
Totals > Grand Totals
5. Add the Allocation and Hard Allocation Totals columns
6. Add 10 days to the Totals columns
7. 10 days are added to the Staff allocation period, June 2023
8. Change the effort to FTE
9. Add 1 FTE to the totals column
Expected Results: 1 FTE is added to the June period when the Staff member is allocated
Actual results: 3 FTE are added to the month of June
Note: The FTE value added to the period equals the number of periods visible on the grid
This is caused by DE70143
This is fixed in 16.2.0