Issue/Introduction

  • There is an option to copy Status Reports in Classic UI
  • It is also possible to trigger a Process to work on a Status Report instance. Have it copy Status Report or implement other functionalities
  • Is it possible to do these actions in Modern UX?

Environment

Clarity 16.1.1, 16.3.1.

Resolution

  • There is a tab in the Modern UX called 'Status Report'. This has functionality to copy Status Reports from the UI. This tab is deprecated. It is not recommended for use
  • The 'Status' tab in Modern UX is recommended for use. Here there is no option to manually copy Status Reports. Values are copied across to the new Draft report when the old Draft report gets published
  • It is not possible to trigger a Process using Actions in Modern UX, for Status Reports. Alternatively, a trigger condition can be defined, that kicks off a Process automatically in the background, upon fulfilment of this trigger condition.