MUX Common Grid Per Period Metrics Grand Totals are not exported to CSV
search cancel

MUX Common Grid Per Period Metrics Grand Totals are not exported to CSV

book

Article ID: 263450

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

In MUX, on Assignment module, the Per Period Metrics Grand Totals will not export to CSV / Excel, whatever View configuration we do - Months, weeks etc. Grand Totals never gets exported

STEPS TO REPRODUCE:

  1. Add the Assignments module to the Project Blueprint
  2. Open a project that covers at least 1 year
  3. Add Per Period Metrics - Weeks - Covering 52 weeks - ETC and Actuals - Grand Totals
  4. Make sure Grand Totals column is also added to the view
  5. Note all assignments data for Actuals and ETC is displayed, also the Grand Totals
  6. Now click on the Export to CSV icon to download the excel file

Expected Results: The Grand Totals columns should be in the resulting Exported CSV file

Actual Results: The Grand Totals columns are not getting exported

Workaround: None

Note this also happens on Staffing module and other modules

Environment

Release : 16.1.1

Resolution

This is DE69234, fixed in 16.1.2