In Classic PPM on a Project or within the PPM Gantt, you can use an action 'Copy Tasks From Template'.
Release 15.x, 16.x
Question | Answer |
In Classic PPM can you copy tasks from regular projects instead of a Template? | Yes, you can change the filter in the Project Selection page to filter for non-template projects. |
Can you copy tasks from within the same project as the target? | Yes, you can change the filter in the Project Selection page to filter for the current project to copy existing tasks again within the same project. Only tasks without a Task ID will be successfully copied because you cannot copy a task with the same Task ID that already exists in this project. Attempting to copy a task that has the same Task ID of an existing task on the target investment is not copied and no message is generated to the user. |
Can you copy an Effort Task from the source investment to the target investment? | If the Target investment does NOT already have an effort Task (ID = ~rmw) then it is copied. |
Can you copy a source investment Task with a Task ID value (either manually entered or auto-numbered)? | If the target investment does NOT already have a Task with that same ID, then it is copied. No message is provided if the task with that ID already exists. When the Task ID field is auto-numbered it is copied the first time using the existing Task ID. A new auto-number is NOT generated when creating the 'copied' task record and hence if the target investment already has the same ID, the task cannot be copied a second time. |
Are Task Dependency lines copied? |
Yes, If you select from the Source investment both the predecessor and successor Tasks, then the task dependency lines will be drawn. If you copy 1 of the tasks (predecessor or successor) that has a dependency and it is linked to a Task that was NOT selected, but the linked task has a Task ID of an existing Task in the Target investment, the Dependency line is drawn between the newly copied task and the existing task on the Target investment. If you copy a task from within the same investment that is linked to another task, the dependency lines are not drawn if the dependent task is also not selected (no task IDs on the tasks). If you copy both predecessor & successor tasks from within the same investment, the new tasks created will have dependencies between the new, copied records. |
If the source project has an 'External Task' listed in the PPM Gantt, can I select it for copy? |
No. You cannot select an 'External Task'. You can only see it on the PPM Gantt as a line item designated as an external task dependency. |
Are Task 'Assigned Resources' (Staff) copied? |
Yes. Regardless of the Target Investment's Assignment Pool Setting, if the assigned resources are NOT already on the target investment, they are added to the Staff. |
Are Proxy SubProject Tasks copied? |
The user is allowed to select a Proxy Subproject Task, but it is NOT copied. No message is provided. |
If you select a Phase or Summary Activity Task are all the child tasks automatically copied? |
Yes, If you pick the Phase or Activity Task and selectively pick some child tasks, it will still bring in ALL child tasks. |
If you select a child task under a Phase or Summary Activity Task, is the Phase or Summary Task copied? |
No. We don't copy (up) the parent tasks. We copy the selected task and if there are children tasks, all those tasks are copied (down). |
What happens to the Task Dates when it is copied to a target investment? Does it impact the overall target investment date range? |
Clarity determines the interval from the start of the source investment to the start of the source task and keeps that when adding it to the target investment. |
What happens to the Actuals on a source Task when it is copied to a target investment? |
Actuals are converted into ETCs. |
What happens to % Complete and Task Status when it is copied to a target investment? |
The % Complete is reset to 0% and the Status is reset to 'Not Started'. |
What happens to the To Dos, Links and Conversations on a Task when it is copied to a target investment? |
Links are copied. |
What happens if I copy a source Task multiple times to the same target investment (without a Task ID) that has an assigned role? |
The Role is added multiple times to the Staff (DBA, DBA2, DBA3, etc). |
What happens if there are active blueprint rules for the Tasks when a Copy Task action is invoked? |
The blueprint business rules are ignored. The 'Copy Tasks' functionality pre-existed before Blueprints. We are allowing multiple tasks to be copied so it does not make sense for the blueprint rules to run for the 'copy' action. |
Are Task local Picklist values copied? |
No. Task Picklist definitions are unique to each investment. |
Task ID field | ‘Copy from…’ Action (introduced in Release 16.1.2) | NEW! Context ‘Copy’ action within the same Investment |
Blank | Task is copied. Task ID = blank. The task can be copied multiple times to the target investment. | Task is copied. Task ID = blank |
Manually-entered value | If the target investment does NOT already have a Task with that same ID, then it is copied. No message is provided if the task with that ID already exists. | Task is copied. Task ID = blank |
Auto-Numbered | When the Task ID field is auto-numbered it is copied the first time using the existing Task ID. A new auto-number is NOT generated when creating the 'copied' task record and hence if the target investment already has the same ID, the task cannot be copied a second time. | Task is copied. Task ID = newly-generated auto-numbered value |
An issue has been identified with Release 16.2.0 'Copy' context action with regard to the Task Status and % Complete fields are not getting reset as expected on the newly copied task.
Reference Knowledgebase Article # 275908 for more details.