Steps to Reproduce:
1. Create a Project Template and Financially Enable it
2. Add a Cost Plan
3. Add Tasks
4. Create Idea and set it to Approved status
5. Convert this idea using template created in step 1 with below 3 optionsed checked.
Copy Team
Copy Financials
Copy Risks, Issues and Changes
Expected Results: it should copy Tasks and Financials to a newly created project
Actual Results: it does not copy Tasks and Financial to a newly created project
Release : 16.1.1
This is caused by DE68767
This is fixed in 16.1.1.1 and 16.1.2