Modern Project > EAC Field Is Blank
search cancel

Modern Project > EAC Field Is Blank

book

Article ID: 260455

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

The EAC field is blank, null, not populating in the project task view.
There are  hours in the plan.
Is there anything else that needs to be set in order for the EAC field to populate?

 

Environment

Release : 16.0.3

Resolution

The prerequisites for populating the field and its related fields are:
Create a baseline.
Update the baseline.

Additional Information

Instead of EAC, EAC(T) is recommended to be used instead.
It denotes EACTotal

Documentation Referenced: Update Project Task Cost Totals