Money Metrics on the Hierarchy view are not correct when using Spanish language
search cancel

Money Metrics on the Hierarchy view are not correct when using Spanish language

book

Article ID: 260304

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Money Metrics on the Hierarchy view are not correct when using Spanish language

In US 1.000.000.000 USD is a Billion
In Spain the same figure is a Milliard or Thousand Millions

In US 1.000.000.000.000 USD is a Trillion
In Spain the same figure is a Billion

STEPS TO REPRODUCE

1. Create a project with a planned cost of 1.000.000.000
2. Create a project with a planned cost of 1.000.000.000.000
3. Create a Hierarchy in MUX and import the above 2 projects
4. On the Hierarchy > Investments > Board > View Options
   Add the Planned Capital Cost field to the board
   Add the Planned Capital Cost metric to the board   
5. Go to the user settings and using English language look at the Hierarchy Board
   Project 1 shows the metric as 1B
   Project 2 shows the metric as 1E3B 


6. Go to the user settings and using Spanish language look at the Hierarchy Board

Expected Results:
   Project 1 shows the metric as 1000M or 1 Millardo
   Project 2 shows the metric as 1B
Actual Results: 
   Project 1 shows the metric as 1G
   Project 2 shows the metric as 1E3G

Cause

This is caused by DE68561

Resolution

This is fixed in 16.1.2

Additional Information

This might affect other languages too i.e Czech

Attachments